Thailand's New Data Center Framework: Cabinet Approves Regulatory Policy – Seven Tiers, Minimum Requirements, and Competitive "Pitching" for New Projects

Thailand's New Data Center Framework: Cabinet Approves Regulatory Policy – Seven Tiers, Minimum Requirements, and Competitive "Pitching" for New Projects

In our newsletter of 18 August 2026, we reported on the establishment of the Data Center Business Policy Committee (the "Committee") under the Prime Minister's Office Regulation on the Data Center Business Policy Committee B.E. 2569 (2026) (the "Regulation"). We noted then that the Committee's detailed policy package had not yet been issued. On 27 October 2026, at Meeting No. 4/2569, the Committee approved the draft Policy on the Regulation of Data Center Business and submitted it to the Cabinet. On 10 November 2026, the Cabinet approved the policy (the "Policy").

Until now, there have been no specific rules for data centers. Each agency has approved projects under its own powers by analogy to similar businesses, such as warehouses or large buildings. The relevant agencies have also suspended the granting of approvals, permits, and Board of Investment ("BOI") promotion certificates for data centers pending a new framework. The Policy introduces centralized screening so that the country's electricity and water are allocated to projects that bring the greatest benefit to Thailand.

i.Definition and Seven-Tier Classification

The Policy broadens the definition of "data center." It now covers buildings, premises, or structures that use electronic equipment to collect, store, process, host, or transmit data, whether for the operator's own business or its affiliates, or to serve third parties that are not affiliates, provided that the total electricity demand (Facility Load) is 0.5 megawatts ("MW") or more. As a result, large enterprise and in-house data centers now fall within the Policy, not only colocation and cloud facilities.

Data centers are classified into seven tiers by electricity demand:

TiersElectricity DemandRegulatory Treatment
1Below 0.5 MWOutside the scope of the Policy
20.5 MW to below 5 MWSubject to the Minimum Requirements, with stringency increasing by tier
35 MW to below 10 MWSubject to the Minimum Requirements, with stringency increasing by tier
410 MW to below 20 MWSubject to Minimum Requirements, with stringency increasing by tier
520 MW to below 50 MWSubject to the Minimum Requirements, with stringency increasing by tier
650 MW to below 200 MWSubject to the Minimum Requirements, with stringency increasing by tier
7200 MW and aboveSubject to the most stringent Minimum Requirements

At the press briefing, the Government also indicated that data centers below 20 MW may be located in commercial zones, while those of 20 MW or more will be limited to industrial zones.

The Committee has established four subcommittees, covering:

  1. economic matters, data integration, and the ecosystem (the “Economic Subcommittee”), chaired by the Minister of Digital Economy and Society;
  2. infrastructure, chaired by the Minister of Energy;
  3. area, town planning, buildings, and structures, chaired by a Deputy Minister of Interior; and
  4. environment, chaired by the Minister of Natural Resources and Environment.

ii.Minimum Requirements and the Code of Practice

The Policy sets minimum technical requirements (the "Minimum Requirements") specifically for data centers. They cover four dimensions: (1) economic; (2) infrastructure; (3) area, town planning, buildings, and structures; and (4) environment. Some of these go beyond existing laws and regulations, so relevant agencies must first prepare or amend the applicable rules, including through public consultation. The whole process is expected to take about one year. This includes 8–12 months to amend comprehensive town plans under Section 35 of the Town Planning Act B.E. 2562 (2019). It also includes about one month for the Office of Natural Resources and Environmental Policy and Planning ("ONEP") to revise the draft Code of Practice ("CoP"), excluding the legislative steps needed to bring it into force.

Fees charged to data center operators for resources such as electricity, raw water, and tap water must reflect both direct and indirect costs.

CoP instead of EIA. According to the Government's press briefing, data centers will generally not be required to prepare an environmental impact assessment ("EIA"). Instead, the CoP is expected to control backup-generator noise (no more than 70 decibels at the project boundary), the temperature around the building (a rise of no more than approximately 1–2°C), and the quality of cooling water before discharge. Data centers within an industrial estate must comply with the EIA of that estate.

Backup power and reserve fuel. Facilities designed to the Uptime Institute’s Tier IV standard must store enough diesel to run generators at full load for at least 24–72 hours without external refueling. Because large fuel stores pose public safety risks, particularly fire, operators will be given time to shift to batteries or other technologies that are safer than fuel storage.

iii.Transitional Framework

The cut-off date is 14 August 2026, the date on which the Regulation took effect. During the transitional period, approvals will be handled as follows:

CategoryTreatment
1.Construction permit (Aor.1, or notification under Section 39 bis of the Building Control Act B.E. 2522 (1979)) obtained by 14 August 2026, or expansion keeping total demand below 20 MW
Considered for approval under current laws and regulations. Must meet the environmental and economic Minimum Requirements within one year of the date on which the Cabinet announces the Minimum Requirements.
2.BOI promotion obtained by 14 August 2026
Considered for approval under current laws and regulations. Must meet the environmental Minimum Requirements only, within one year of the Cabinet's announcement.
3.Construction permit obtained after 14 August 2026, no construction permit, or an operating data center expanding to total demand of 20 MW or more
Treated as a new operator. Must fully meet the Minimum Requirements to be announced by the Cabinet.

New operators in Category 3 that can adjust their investment to meet the Minimum Requirements may be approved without waiting for the legal amendments to be completed.

BOI-promoted projects. As reported following the Cabinet meeting, the BOI had approved investment promotion for 57 data center projects as of April 2026. Of these, about 17 are in operation, 20 have obtained construction permits, and 20 are preparing to invest. The BOI indicated that these projects will be considered by the BOI Board and the Data Center One Stop Service ("DC-OSS") under the new criteria. How this will apply to BOI-promoted projects in Category 2 remains to be clarified. These figures cover BOI-promoted projects only and are not directly comparable to the overall pipeline figures in section iv.

iv.Centralized Screening and Competitive "Pitching"

The Policy introduces a centralized screening and monitoring mechanism, DC-OSS. A screening committee will be established to screen, monitor, and evaluate data center projects, including reviewing CoP reports both before and during operation. However, the Regulation does not currently give the Committee centralized screening powers. It must first be amended, which is expected to take about one month.

Until the necessary laws are in place, the Ministry of Digital Economy and Society ("MDES") will perform the screening role. Relevant agencies will submit approval data to MDES through the TH-DC Dashboard. Where MDES finds that all approvals are complete and there is no adverse impact on national resource allocation, it will notify the provincial governor, who will approve the opening of the data center.

The screening committee may require proposals to be submitted through a Pitching process, under criteria that the Committee will announce from time to time. The Policy supports data centers whose investment plans include:

  • alignment with Thailand's Net Zero 2050 goal (Green Data Center);
  • partly or fully self-procured resources;
  • greater use of local labor and Thai components;
  • investment in the digital and related industries in Thailand; and
  • booking revenue in Thailand for corporate income tax purposes.

The Economic Subcommittee will set the detailed criteria before they are proposed to the Cabinet. At the press briefing, the Government said this approach follows one used in Singapore.

As of September 2026, the pipeline was as follows:

  • In operation: about 63 data centers, 16 of which had signed power purchase agreements ("PPAs") totaling 739.12 MW, with 101.24 MW being supplied at the time;
  • Under construction with permits obtained before 14 August 2026: about 20 projects, with signed PPAs totaling 1,645.70 MW;
  • Under construction or applying for approvals: about 27 projects, 9 of which reported demand totaling 856.72 MW; and
  • Applying or interested: about 89 projects, with total demand of 26,647.4 MW.

v.TH-DC Dashboard and Agency Timelines

There is currently no central record of data centers in Thailand. Around 18 agencies are involved in approving them, and no law requires operators to register. MDES will develop the TH-DC Dashboard to consolidate project, approval, and power and water demand data. MDES will also draft legislation requiring operators to register on the TH-DC Dashboard.

Each relevant agency must review its processes to align with DC-OSS. It must also specify clear timelines for each approval step (a Service Level Agreement, or "SLA") and process approvals digitally as far as possible.

Separately, the Bangkok Metropolitan Administration ("BMA") monitors noise, heat, wastewater, and fire safety at Bangkok data centers. It has warned that it will order an immediate halt to operations if it finds actual harm to the public.

vi.Practical Implications

1.Scope review: Enterprise and in-house data centers of 0.5 MW or more are now within the Policy. Operators should assess whether their facilities are covered.

2.Pipeline projects: Treatment depends on whether a project held a construction permit or BOI promotion by 14 August 2026. Permit holders must meet both the environmental and economic Minimum Requirements, while BOI-promoted projects must meet the environmental requirements only.

3.Approval timing: Agencies have suspended approvals pending the new framework. Project timelines and financing milestones should allow for the amendment of the Regulation and MDES's interim screening.

4.Site selection: Based on the press briefing, projects of 20 MW or more are expected to be limited to industrial zones. This should be factored into land acquisition and feasibility studies early.

5.New projects: Investors should prepare for Pitching by building a credible case now on clean energy, self-procured resources, local labor and components, digital-industry investment, and Thai tax presence.

6.Existing operators: The one-year window is short. Gap analyses on the environmental Minimum Requirements, generator noise, heat, cooling-water discharge, fire safety, and the transition away from large fuel stores should begin now.

7.Transactions and financing: Transaction documents should address change-in-law risk through regulatory material adverse change provisions, flexible conditions precedent, and long-stop dates. Buyers should conduct due diligence on each target facility's tier, zoning, permit and BOI promotion dates, and readiness to meet the Minimum Requirements.

vii.What to Watch

  • The amendment of the Regulation to give the Committee centralized screening powers;
  • The Cabinet's announcement of the Minimum Requirements, which starts the one-year compliance period;
  • The Pitching criteria to be set by the Economic Subcommittee;
  • The CoP and town plan amendments;
  • How the BOI will apply the new criteria to its existing promoted projects; and
  • The legislation requiring TH-DC Dashboard registration, to be drafted by MDES.

This newsletter is based on publicly available information, including the Government's official summary of the Cabinet meeting of 10 November 2026, and does not constitute legal advice.