Legacy Renewable PPAs: Proposed Price Review and Automatic Renewal Arrangements

Legacy Renewable PPAs: Proposed Price Review and Automatic Renewal Arrangements

On 8 July 2026, the Committee to Consider Solutions to Issues Arising from Electricity Purchases from Private Power Producers (the “Committee”), with the Office of the National Economic and Social Development Council (“NESDC”) providing secretariat support, reported that it had approved, in principle, a resolution to review legacy power purchase arrangements with private power producers, particularly those relating to renewable energy projects under the SPP and VSPP frameworks.

Background

Thailand’s private power procurement framework has historically relied on long-term PPAs between private power producers and state utilities, including the Electricity Generating Authority of Thailand, the Metropolitan Electricity Authority and the Provincial Electricity Authority. Renewable energy projects have generally been developed under the SPP and VSPP frameworks, with purchase and pricing arrangements varying by sources, technology, procurement round and applicable support scheme.

Since 2007, many legacy renewable projects were developed under earlier support mechanisms, including the Adder regime and earlier FiT arrangements, during a period when then-prevailing  renewable technology costs were higher than current market levels. Certain legacy SPP/VSPP renewable PPAs reportedly continue to be priced by reference to the wholesale electricity price plus Ft, resulting in purchase prices exceeding THB 3.00/kWh. Older PPAs also appear to include mechanisms that allow extension or automatic renewal after expiry of the original PPA term.1

By comparison, recent renewable procurement rounds have generally moved towards fixed FiT pricing for defined PPA terms. Current FiT benchmarks for new renewable projects include THB 2.1679/kWh for ground-mounted solar, THB 3.1014/kWh for wind, THB 2.0724/kWh for biogas from wastewater or waste, and THB 2.8331/kWh for ground-mounted solar with BESS. The proposed revised price of THB 2.16/kWh therefore appears to be intended to align certain legacy solar tariffs more closely with the current solar procurement benchmark. Solar generating projects are expected to be the first, and most immediately, affected by this policy change.

The NESDC’s proposal follows Prime Minister’s Order No. 137/2569, issued in May 2026, which established the Committee, chaired by Deputy Prime Minister Pakorn Nilprapunt. The committee includes representatives from key energy, legal, economic and consumer protection agencies, and its mandate includes considering approaches to address PPA terms that may no longer align with current circumstances or fairness principles, with a view to reducing long-term electricity cost burden borne by consumers.

Government Proposal

Based on current reports, the proposal would affect the following categories of power producers.

     1.    Projects whose 25-year PPAs have expired

     For renewable power plants whose initial 25-year PPAs have expired but continue to operate under automatic renewal arrangements, the Government reportedly proposes to end automatic renewal going forward. One final extension may be allowed for the renewal period originally provided for under the PPA, such as three or five years. However, any such extension would be subject to a revised purchase price of THB 2.16/kWh. After that final extension, the PPA would terminate.

     2.    Projects that have received Adder support for 10 years

     For projects that have already received Adder support for 10 years, with a remaining term under their PPAs, the Government proposes to reduce the purchase price for the remaining term to THB 2.16/kWh.

     The policy rationale appears to be that these projects have already benefited from the Adder support mechanism and that the purchase price for the remaining term should be adjusted to reflect current renewable energy costs.

     3.    Delayed non-COD projects

     For projects that have not yet achieved COD and have been delayed for more than two years, the Government may consider termination on a case-by-case basis.

     4.    IPP contracts

     IPP contracts do not appear to be the immediate target of the current proposal. However, the Committee has resolved to establish a separate subcommittee to review availability payment (AP) and energy payment (EP) structures under IPP contracts.

Status

Whether the Government will proceed from policy review to formal action affecting existing PPAs remains an open question. At this stage, the Committee’s proposal has not yet become a legally binding measure. The Committee’s resolution would need to be submitted to the National Energy Policy Committee for approval before the relevant authorities and state utilities can proceed with implementation. Given the potential impact on existing contractual rights, consultation with the Office of the Council of State may also be required.

Any unilateral change to existing PPA terms or termination by an administrative counterparty would raise significant legal issues. PPAs with state utilities are administrative contracts, and while state utilities may have certain public-interest powers, these powers must be exercised within established legal frameworks. The Government appears to recognise that Thai administrative law provides certain protections for private parties in circumstances where their contractual rights and interests are affected by the exercise of powers. Similarly, a government policy announcement or administrative direction should not, by itself, be assumed automatically to amend the commercial terms of existing PPAs, unless and until it is given legal effect through applicable legislation, regulation or formal administrative action. Affected parties should monitor how the policy develops and whether the Government proposes any offsetting measures or incentives to address stakeholder concerns.

Affected Parties

Affected power producers and generators should determine whether their PPAs fall within the categories set out above and review their existing PPA terms to assess how the proposed policy and revised purchase price, if implemented, may affect their projects. Sponsors should consider any capital expenditure they are likely to incur in the near term, prepare sensitivity analyses for various cash-flow scenarios, and review force majeure, change-in-law and termination provisions in their PPAs and financing documents to identify available remedies and notification requirements.

For financial advisers and investors, this may warrant a reassessment of asset valuations, particularly for portfolios with exposure to legacy renewable projects in Thailand; due diligence on new acquisitions should factor in the policy risk, and financial advisers and investors may need to update IRR and equity return projections for existing investments under downside scenarios.

Lenders to affected projects should evaluate the financial implications for base-case models, project cash flow, debt service and debt service coverage ratios, particularly for projects that have been recently refinanced, regeared or whose debt tenor extends into the next three to five years. Lenders should also consider whether any potential purchase price reduction could result in breaches of financial covenants or trigger cash sweep events under existing facility agreements, and whether reserve account balances would remain adequate under stress scenarios.

Chandler Mori Hamada will continue to monitor these developments and keep clients informed of further updates. If you have any questions in relation to the issues raised in this newsletter, please contact the authors listed above.

 

__________________________________________________________________________________________________________________

1Based on current reports, the pool of potentially affected legacy renewable PPAs includes approximately 515 PPAs for projects whose initial 25-year PPA terms have expired, but which remain in effect under automatic renewal terms of three to five years. These PPAs represent aggregate capacity of around 2,400 MW. In addition, there are approximately 46 PPAs for projects that have already received Adder support for 10 years but still have time remaining under their 25-year PPAs, representing COD capacity of around 1,478 MW. A smaller group of non-COD projects, comprising approximately four PPAs with aggregate capacity of around 67 MW, may also be reviewed where COD has been delayed for more than two years with no apparent progress.